We are pleased to announce that we have awarded the kayak launch construction contract to Landivar and Associates, and the project will break ground early in the coming year. The construction timeline is detailed below.
We still need support to get to the finish line -- a total construction cost of $542,486. You can help us close a $40K gap with a year-end contribution!
Here's what to expect as we build and open the DC metro area's first free public ADA-accessible Potomac River paddling access:
- March 2025: groundbreaking and site preparation
- April 2025: installation of helical piles and concrete abutments
- May 2025: installation of boardwalk decking/railings
- May-June 2025: attachment of gangway and floating launch
- June 2025: OPENING